The Ministry of the Sea, Transport and Infrastructure (MMPI) actively participated in the use of available EU funds through the financial period 2014-2020. The improvement of the website was co-financed by technical assistance funds from the Operational Program Competitiveness and Cohesion, from the European Regional Development Fund. The content of this site is the responsibility of the Ministry of the Sea, Transport and Infrastructure.

X-Pand COEN

Expanding the charger network X-Pand COEN

Source of funding

CEF 2

Completion phase:

Project implementation

Total eligible costs (EUR)

1.341.176,47

EU contribution (EUR)

1.140.000,00

Date of conclusion of the contract

11.06.2025

Estimated completion date

10.09.2028

Project description

The project envisions the deployment of 35 recharging pools (sites) equipped with 182 recharging points of a minimum power output of 150 kW for LDV and 8 recharging pools (sites) equipped with 32 recharging points of a minimum power output of 350 kW for HDV.

Project goal

The main objective of this project is to deploy an operational network of recharging pools publicly accessible 24/7 for Light-Duty Vehicles (LDV) and Heavy-Duty Vehicles (HDV). It will enhance electric recharging service along the TEN-T road networks in Croatia, Bulgaria and Poland.