The Ministry of the Sea, Transport and Infrastructure (MMPI) actively participated in the use of available EU funds through the financial period 2014-2020. The improvement of the website was co-financed by technical assistance funds from the Operational Program Competitiveness and Cohesion, from the European Regional Development Fund. The content of this site is the responsibility of the Ministry of the Sea, Transport and Infrastructure.

Reconstruction of the Puntin pier – port of Korčula

Reconstruction of the Puntin pier – Port of Korčula

Source of funding

OPCC

Completion phase:

Completed project

Total eligible costs (EUR)

1.396.210,76

EU grant (EUR)

1.186.779,15

Date of conclusion of the contract

29.07.2019

Project completion

15.03.2022

Project summary

The project envisages the reconstruction of the Puntin pier on the western shore of the Port of Korčula with the aim of improving the quality of maritime public transport and increasing the safety of passengers on the year-round high-speed lines 9807 Lastovo – Korčula – Polače – Sobra – Šipanska Luka – Dubrovnik and 9608 Korčula – Prigradica – Hvar – Split and the conventional service 614 Korčula – Orebić (Pelješac).

Project activities include the improvement of the foundation soil, reinforcement and binding of the pier construction, removal of the inadequate seawall, construction of a new layered seawall and construction work to permanently secure the pier against damage and deformation. The implementation of the project shall ensure the long-term sustainability of the year-round transport service for the local population and improve the maritime connections of the island of Korčula.