Project description
The project includes investments in:
- a floating (pontoon) breakwater Pier 1 with a 73.95 x 4.00 m footprint, designed as a segmented structure with seven ten-meter spans between modules,
- floating piers 1a and 1b, situated between the northern shore and Pier 1, composed of floating elements on pontoons,
- the reconstruction of the northern shore (approximately 168,40 m long and 7,90 m wide) and the Markantun Dominis Promenade (approximately 144,82 m long and 7,80 m wide),
- the reconstruction of the 450 m port access road in the port area between the DM store and Slavija Public Parking, with required roadside infrastructure,
- the reconstruction and resurfacing of the 650 m long, 8 m wide road between Slavija Public Parking and Cape St. Anthony, adjacent to the previously reconstructed access road.