The Ministry of the Sea, Transport and Infrastructure (MMPI) actively participated in the use of available EU funds through the financial period 2014-2020. The improvement of the website was co-financed by technical assistance funds from the Operational Program Competitiveness and Cohesion, from the European Regional Development Fund. The content of this site is the responsibility of the Ministry of the Sea, Transport and Infrastructure.

Upgrade of the Rijeka Port infrastructure – AGCT dredging

Improving the infrastructure of the port of Rijeka – dredging of the south berth

Source of funding

CEF

Completion phase:

Completed project

Total eligible costs (EUR)

17.389.436,00

EU contribution (EUR)

2.782.310,00

Date of conclusion of the contract

20.12.2018

Project completion

25.04.2025

Project summary

The project funded the removal of the bottleneck caused by significant limitations of the Adriatic Gate Container Terminal (AGCT). The implementation has improved the efficiency of cargo handling on the terminal and raised sea depth along the terminal, enabling the berthing of larger vessels.

The project activities included upgrading the existing infrastructure by dredging works and ancillary interventions along 100m of the Phase I quay wall, bringing it to the same 14,88m sea depth as the adjacent 328m Phase II quay wall. This has resulted in a 428m quay wall with a sea depth of 14.88m, thus enabling the accommodation of bigger container vessels.